What it is
A one-hour pre-mortem workshop based on Gary Klein’s method (Harvard Business Review, 2007). Your team imagines the project has already failed and works out why.
What it helps you achieve
Surface risks people rarely raise in regular meetings
Turn the top risks into actions with an owner, a due date and an early warning signal
Start the project with a shared, realistic view of what could go wrong
Who it’s for
Project and delivery managers, Scrum Masters, tech leads and project teams of 5–9 people. Use it at kickoff, before a major release, or whenever a plan feels too optimistic.
How to use it
Before the session: fill in Step 1 (objective, deadline, stakeholders, success criteria) and set the date in the Step 2 banner.
Step 1 · 5 min: read the objective aloud.
Step 2 · 20 min: read the ground rules, run the 10-minute silent writing timer, then have everyone read their stickies aloud.
Step 3 · 20 min: group similar stickies into clusters and vote (3 votes per person).
Step 4 · 20 min: move the 3–5 top-voted clusters into the table and agree on an action, owner, due date and early signal for each.
The board includes a facilitator guide and a filled example for a fictional FinTech project.