Project Pre-Mortem

5views
0uses
0likes

Report

What it is

A one-hour pre-mortem workshop based on Gary Klein’s method (Harvard Business Review, 2007). Your team imagines the project has already failed and works out why.

What it helps you achieve

  • Surface risks people rarely raise in regular meetings

  • Turn the top risks into actions with an owner, a due date and an early warning signal

  • Start the project with a shared, realistic view of what could go wrong

Who it’s for

Project and delivery managers, Scrum Masters, tech leads and project teams of 5–9 people. Use it at kickoff, before a major release, or whenever a plan feels too optimistic.

How to use it

  1. Before the session: fill in Step 1 (objective, deadline, stakeholders, success criteria) and set the date in the Step 2 banner.

  2. Step 1 · 5 min: read the objective aloud.

  3. Step 2 · 20 min: read the ground rules, run the 10-minute silent writing timer, then have everyone read their stickies aloud.

  4. Step 3 · 20 min: group similar stickies into clusters and vote (3 votes per person).

  5. Step 4 · 20 min: move the 3–5 top-voted clusters into the table and agree on an action, owner, due date and early signal for each.

The board includes a facilitator guide and a filled example for a fictional FinTech project.